REQUIRED INSPECTIONS DURING CONSTRUCTION

We will need to see the following stages of construction:

 

  1. Footing in place
  2. Foundation with drain tile and not back filled.
  3. General framing, flashing and sheathing membrane installed before siding.
  4. Outside finish generally complete including fireplace/flue, rough plumbing and insulation/vapor barrier but "not gyproc."
  5. Occupancy - Exterior and interior of structure completed.

STAGE A: Subfloor plumbing and rebar.

STAGE B: Subfloor and foundation insulation/Radon barrier & pipe.

You are legally responsible for notifying the Building Department at the above mentioned stages so that any problems can be corrected before they become costly.